Defects liability period: how to manage snags after practical completion (JCT and NEC)

Handover is not the end of the snag list. It is the start of a second, slower phase where defects are reported by people who were not on the walk-around, and where the record you keep decides how smoothly the project reaches its final certificate.

The key point

The defects liability period is the period after completion during which the contractor must come back and put right defects that are notified to it. Modern JCT contracts call it the Rectification Period. NEC contracts do not use either term: they set a defects date, which is the last date for notifying a defect, and a defect correction period for fixing each one. Neither period ends the contractor's liability for defects nobody has found yet. What the period does control is the paperwork that releases retention and closes the account, so the practical job is a defects register where every item has a notification date, an owner, evidence of the fix and a clear accepted or rejected status.

This guide is general information, not legal advice. Always check the wording and any amendments in your own contract.

The same idea under three names

People still say "defects liability period" on site, whatever the contract says. That is understandable, but the terms carry different mechanics.

  • JCT: Rectification Period. In a post on the JCT blog, Hugh Saunders of 3PB notes that modern JCT contracts use the term Rectification Period, even though "defects liability period" is still in everyday use. By default, the contractor must make good "defects, shrinkages or other faults" that are notified to it in time, at no cost to the employer.
  • NEC: defects date and defect correction period. An article on NEC Contracts' own website, by Richard Patterson of Mott MacDonald, is blunt: there is no "defects period" and no "defects liability period" in NEC. The contract data states a period in weeks (usually 52) from completion of the whole of the works to the defects date. That is the last date for the Supervisor to notify a defect or instruct a search for one. Each defect then has to be corrected within its defect correction period.
  • NEC has no "snags" either. The same NEC article says there are only defects: "big" ones that stop the client using the works and so hold up completion, and "little" ones that do not. Completion can still be certified with little defects outstanding, which is exactly why a post-completion register matters.

If your team works on both JCT and NEC jobs, it is worth agreeing which words your register uses, so that "notified", "corrected" and "closed" mean the same thing on every project.

What the period does, and does not, do

It does not end liability. Saunders warns that the name can suggest liability for defects ends when the period expires, and that some clients have been surprised to receive claims afterwards. Under JCT, liability for latent defects survives even after a certificate of making good, because the certificate relates only to defects notified within 14 days of the end of the Rectification Period. On the NEC side, the NEC article explains that a "defects liability period" only really exists if Option X18 is used, which sets an "end of liability date", usually 12 or 6 years after completion.

It does drive the money. Under JCT, once the certificate of making good is issued the contractor becomes entitled to claim the retention, and the clock starts for the Final Certificate. Saunders points out that slow certification leaves the contractor unable to claim retention and delays the Final Certificate, which is where tempers fray. Under NEC4, Sharpe Pritchard explains that the Supervisor issues the Defects Certificate on the defects date if every notified defect has been corrected, or otherwise at the earlier of the end of the last defect correction period and the date the last notified defect is corrected.

It sets the clock for each defect. Under NEC4, the defect correction period starts at completion for defects notified before completion, and at notification for defects notified afterwards. Sharpe Pritchard adds that different correction periods can be set for different categories, for example a shorter period for defects that pose a health and safety risk. In other words, the notification date on each item is not admin. It is the start of a contractual clock.

What happens if a defect is not put right

Both contracts give the client a route when a defect is not corrected, and both depend on the record.

  • JCT. The employer can choose not to have the contractor make good, and instead make an "appropriate deduction" from the contract sum. Saunders notes this deduction could be more than the outstanding retention, and that it is an obvious place for a dispute to start.
  • NEC4. Sharpe Pritchard explains that if the contractor was given access during the defect correction period and did not correct the defect, its liability is the cost, assessed by the Project Manager, of having it put right by someone else. If the contractor was not given access, its liability is limited to what it would have cost the contractor to do the work itself.

Notice the detail that matters in the NEC case: whether access was given. That is a fact you will only be able to show if access visits and refusals are recorded against the item.

A defects register that gets you to the certificate

Most projects already have a snag list from completion. The defects phase needs a few extra columns and some discipline. For every item, record:

  1. The notification date and how it was notified. Use the contract's own verb. The NEC article says defects are "notified", not "raised", and recommends making notifications separately from other correspondence.
  2. Before or after completion. Under NEC4 this decides when the correction period starts.
  3. Location, description and a photograph. The same standard as any good snag: somewhere a stranger could find it, an observation, and the action needed. Our guide on writing a snag someone can act on covers this.
  4. Category and target date. If your contract sets different correction periods for different categories, record the category and the resulting date.
  5. Owner. The responsible contractor or trade, with one name against the item.
  6. Access arranged. When access was offered, given or refused, especially in occupied buildings and on operational railway or estate sites.
  7. Completion evidence. A photograph from the same position as the original, plus the contractor's note.
  8. Review decision. Accepted, returned or still open, with who decided and when. Keep the history rather than overwriting it.
  9. Queries and disputed items. Keep anything the contractor says is not a defect, or is additional work, visible as a separate status rather than quietly closing or deleting it.

Saunders' practical advice is that both sides should be open and proactive about the defects process, and that contractors should engage in identifying defects during the period rather than waiting for the end. A shared, item-by-item register makes that much easier than a schedule emailed as a PDF a fortnight after expiry.

Where SnagSort fits

SnagSort does not decide what counts as a defect under your contract, and it does not issue certificates. It helps with the record behind them. Site photographs and rough notes become a structured register using the column headings your project already uses. Each contractor gets a scoped portal with only their items, where they can give programme dates, raise queries or additional work with a proposed response, and return completion photographs against the right item. Authorised project members accept, reject or leave items open, with the history kept, and you can produce PDF reports, Excel exports and evidence packs for handover and project records. Contractors responding through the portal do not need a paid subscription.

If your defects list currently lives in an inbox, see how SnagSort works.

FAQ

What is a defects liability period?

It is the period after completion during which the contractor must return to put right defects that are notified to it. JCT now calls it the Rectification Period. NEC uses a defects date and defect correction periods instead.

How long is a defects liability period?

Whatever your contract states. The NEC article says the period to the defects date is usually 52 weeks, and Sharpe Pritchard says the defects date is often 12 to 24 months after completion. Check your contract data or particulars rather than assuming 12 months.

Does the contractor's liability end when the period ends?

No. The JCT blog explains that liability for latent defects survives the end of the Rectification Period, even after a certificate of making good, and there is an argument that it continues for patent defects that were never notified. Under NEC, the defects date is a deadline for notifying defects, not the end of all liability; a separate end of liability date only applies if Option X18 is used.

Is the defects date the deadline for fixing defects under NEC?

No. Sharpe Pritchard notes this is a common misunderstanding. The defects date is the last date for notifying defects. Each defect must then be corrected within its defect correction period.

When is retention released?

Under JCT, the contractor becomes entitled to claim the retention after the certificate of making good is issued. How retention works varies between JCT forms, so check the form you are using.

Is a snag list the same as a defects list?

Not quite. A snag list usually covers items found at or before completion. The defects register covers items notified during the period after completion. In NEC terms both are simply defects; the difference is when they were notified and when the correction clock starts.

Sources

This guide summarises published commentary for general information. It is not legal advice. Contract wording and amendments vary, so check your own contract.