Non-conformance report (NCR) in construction: what to include, how to disposition it and how to close it out

Most NCRs are not hard to raise. The trouble comes later: a vague description, no reference to the requirement that was missed, a disposition nobody approved, and a "closed" status with no evidence behind it. By the time anyone looks, the ceiling is boarded or the contractor has left site.

The key point

A non-conformance report (NCR) is the formal record that work, materials or a process do not meet a specified requirement. A useful NCR has five things: a unique reference, a description and location a stranger could follow, the requirement it fails against, an approved disposition (repair, rework, reject or use-as-is) and close-out evidence reviewed by someone other than the person who did the fix. Raise it as soon as the issue is found, agree what "closed" means before the job starts, and close it before access is lost.

This guide is general information, not legal or contractual advice. Your contract, quality plan and client procedures decide when an NCR is required and who can close it.

What a non-conformance report is for

The Designing Buildings Wiki describes an NCR as "a formal document used to identify, record, and address instances where work, materials, or processes do not meet the specified requirements or standards". Its examples include materials delivered to site that do not meet the specification or are damaged, work that falls short of the project's quality standards, and deviations from approved methods or procedures.

The point is not the form. It is that the deviation is recorded, assessed, put right and checked, and that the record can be analysed later so the same thing does not keep happening.

If you are still deciding whether an item is a snag, a defect or an NCR, start with your contract and quality procedure. That question is about wording. This guide assumes you have decided an NCR is needed and want it done properly.

When to raise an NCR

Your own procedure sets the trigger. Crossrail's is a useful, concrete example. Its Works Information, quoted in the Learning Legacy paper by Daniel Quant, said:

  • where a defect "cannot be put back in compliance within the same shift", the contractor raises an NCR; and
  • where a specified work activity "has not been carried out in accordance with agreed procedural requirements", an NCR is raised.

That second trigger is easy to forget. An NCR is not only about a visibly wrong installation. A missed hold point or an inspection done out of sequence can be a non-conformance too, even if the finished work looks fine.

Crossrail also required every NCR, including subcontractor NCRs, to go into one central system unless the Supervisor accepted otherwise. One register beats several private ones.

What to include in an NCR

Crossrail published a sample NCR form (a test record) as Appendix B to the paper. Combined with the Designing Buildings list, it gives a practical set of fields. You will not need every one on a small job, but each has a reason.

Identification

  • Unique reference. Crossrail used the format CXXX-NCR-000xyz: the contract reference plus a sequential number allocated automatically when the NCR is initiated.
  • Contract, area and discipline. So the item can be routed and reported on.
  • Subject line. A short headline someone can scan in a list.
  • Initiator, date initiated and required close-out date.

The problem

  • Location. Precise enough to find again: level, room or chainage, gridline, asset.
  • NCR details. What was found, written as an observation rather than a conclusion.
  • Reference documents and technical requirement. The drawing, specification clause or procedure the work fails against. Designing Buildings lists "the standards, specifications, or drawings that the work should have conformed to" as core content.
  • Classification. Crossrail's top three classifications were workmanship, incorrect installation and design. Set the classification when you raise the NCR, based on what you know at the time.
  • Photographs and attachments. The paper's lessons call for "comprehensive NCR details, location, classification, drawings, clear picture".

The response

  • Proposed correction and proposed disposition. What the responsible party intends to do.
  • Final disposition. What was actually approved, which may differ from the proposal.
  • Corrective action to prevent recurrence. Separate from the correction itself.
  • Cost and time impact. The sample form records an estimated cost, a severity category based on cost, and whether there is a cost or time impact.
  • Root cause category. Recorded only once the investigation has concluded.

The close-out

  • Evidence for the correction and corrective action, and evidence viewed by the reviewer. The sample form keeps these as two separate fields, which is a good habit: one is what was submitted, the other is what was checked.
  • Date of implementation, date of inspection and inspector.
  • History. Every stage, who acted and when. On the sample form that runs initiate, propose action, review, implementation, inspection.

The four dispositions

The disposition is the decision about what happens to the non-conforming work. The Crossrail paper defines four:

  • Rework. The item is made to conform to the original requirements by completion or correction. At Crossrail, rework went straight to implementation, then inspection and close-out.
  • Reject. The item is removed from its intended use. It may be discarded, destroyed, or downgraded if the downgraded item can be clearly identified and controlled. Also routed straight to implementation, then inspection and close-out.
  • Repair. The item is restored to a safe and reliable condition, even though it still does not conform to the original requirement. At Crossrail this needed engineering input to endorse and record the decision.
  • Use-as-is. The item is accepted because it has been established that it is satisfactory for its intended use. This also needed engineering input to endorse and record the decision.

The distinction that matters is between the first two and the last two. With rework and reject, the end state still meets the specification. With repair and use-as-is, it does not, so someone with design authority has to accept that. At Crossrail the Engineering Manager, with the design consultants where applicable, judged whether a repair or use-as-is solution needed a concession to the infrastructure manager. The Works Information also required any NCR needing a concession or design change to be referred to the Project Manager.

On your project, check who has authority to accept work that does not meet the specification. If the answer is "whoever is on site that day", fix that first.

A simple NCR workflow

Crossrail's NCR module ran through five stages, which suit most projects:

  1. Initiate. Raise the NCR with the details, location, classification and photographs.
  2. Propose action. The responsible contractor proposes the correction and disposition.
  3. Review. The client-side reviewer checks the proposal and, at Crossrail, set the severity category and estimated cost at this stage. Repair and use-as-is go to engineering here.
  4. Implement. The work is done.
  5. Inspect and close. The reviewer checks the evidence and closes the NCR only if it is sufficient.

Two timing rules from the Crossrail Works Information are worth borrowing. First, notify promptly. Second, any agreed remedial action must be finished before further work that "may render the non-conforming item inaccessible, difficult to repair or increase the cost of the repair". In plain terms: do not board over an open NCR.

Root cause: correction is not the same as prevention

Fixing the item is the correction. Stopping it happening again is the corrective action, and it needs a root cause. Crossrail only assigned a root cause category once the investigation had concluded, rather than guessing at the start. Its top root causes were defective construction under workmanship, other workmanship causes, and other design problems.

For the most serious or recurring NCRs, Crossrail ran a separate Quality Incident Event Process, with root cause analysis using its own SPOT-On method (derived from 8D and lean six sigma DMAIC) and an executive sponsor to clear blockers. Most projects will not need that machinery, but they do need a rule for when an NCR is serious or repetitive enough to investigate properly rather than just fix.

Track NCRs as a register, not a pile of forms

Individual NCRs fix individual problems. The register tells you whether the job has a quality problem. Crossrail's periodic Quality Performance Index tracked, among other things:

  • the percentage of NCRs first raised by the contractor (target 95%);
  • the NCR closure rate against overdue NCRs at the start of the period (target above 40%); and
  • the percentage of open or overdue NCRs (target 5% or less).

You do not need a league table to use the idea. A weekly view of open, overdue and recurring categories, by contractor, is enough to see where items are stuck.

Lessons from Crossrail you can apply on any job

The paper's lessons for future projects are short and practical. Adapted for a smaller project team:

  • Agree categories and root cause lists at the start, with everyone. Crossrail had drop-down categories but found it had to re-categorise data for reporting, which the paper calls "time consuming and unnecessary" if the categories are right from the outset.
  • Watch for NCRs stuck at one stage. Monitor the workflow so items do not sit at initiate or engineering review.
  • Give guidance on filling in the form. Good location, classification, drawings and a clear picture save rounds of questions.
  • Close early. The paper warns that waiting risks access constraints, or the people involved leaving the project.
  • Review or audit close-outs to reduce the risk of insufficient evidence.
  • Make the system easy to use, with clear reporting and data export.
  • Raise NCRs as soon as they are found, client and contractor alike, to avoid latent defects being discovered late.

Behind all of this was a cultural point. The paper describes an amended NEC3 mechanism in which contractors were in effect paid to correct defects they notified themselves, while the cost of correcting a defect the client notified first could be disallowed. Whatever your contract says, the lesson stands: if people fear the consequences of raising an NCR, they will not raise it, and the problem turns up after handover instead.

Where SnagSort fits

SnagSort is snagging and close-out software. It is not a quality management system, it does not decide whether an item is a contractual defect or needs a concession, and it does not replace your NCR procedure. What it does help with is the evidence and follow-up that NCRs and snags share.

Site photographs and rough notes become a structured register using the column headings your project already uses. Each contractor sees only the items assigned to them in a scoped portal, can give a programme date, and can handle a query or additional work separately from a normal defect. Completion photographs and notes come back against the right item, and the project team accepts, returns or keeps it open with the history kept. PDF reports, Excel exports and evidence packs are available for handover and project records.

If your close-out evidence currently arrives by email and gets matched up by hand, see how SnagSort works.

FAQ

What is a non-conformance report in construction?

A formal record that work, materials or a process do not meet the specified requirements or standards. It records the issue, the requirement it fails against, the agreed action and the evidence that the action was completed and checked.

What should an NCR include?

At minimum: a unique reference, location, a clear description, the drawing or specification it fails against, classification, photographs, the responsible party, the proposed and approved disposition, corrective action, and close-out evidence with who inspected it and when.

What are the four NCR dispositions?

Rework, reject, repair and use-as-is. Rework and reject leave the works conforming to the original requirement. Repair and use-as-is accept something that does not fully meet it, so they need sign-off from someone with design or engineering authority.

When should an NCR be raised instead of a snag?

Whatever your contract and quality procedure say. As one published example, Crossrail required an NCR where a defect could not be put back into compliance within the same shift, or where a specified activity had not followed the agreed procedure.

Who closes an NCR?

Your procedure names the role. In Crossrail's workflow the NCR was inspected and closed by the client-side reviewer only if sufficient evidence was provided, not by the party who did the work.

What is the difference between correction and corrective action?

Correction fixes the non-conforming item. Corrective action addresses the root cause so it does not happen again. Good NCR forms keep them as separate fields.

Sources

Crossrail figures and targets describe that programme only. They are not SnagSort customer results. This guide is general information, not legal or contractual advice.